Case study · ElectraNet
ElectraNet owns and operates South Australia’s high-voltage transmission network. Daitum plans the thousands of work orders that need a network outage.
Sector Energy transmissionModel Self-servicePlan Rolling outage plan
Faster planning
Freed up in the planning team
More months planned
Planning horizon, up from 13
Once a month, ElectraNet builds a rolling outage plan for the thousands of work orders that need a network outage. The plan has to group outages efficiently so customers see as few interruptions as possible. That means:
Before Daitum, one high-level plan could take weeks, and urgent corrective work wasn’t always planned well.
ElectraNet’s planning rules and KPIs were captured in a Daitum model, with the KPI weightings fully adjustable as the network changes. Work team availability, network risk ratings and outage groupings are uploaded alongside the work orders.
Daitum then chooses the month for each work order and which other work should happen at the same time, respecting every constraint. Planners run what-if scenarios with different KPIs to compare plans.
More efficient outage groupings mean fewer planned outages for the same volume of work, which reduces network risk. Plans are five times faster to build, so planners can test scenarios that were impossible by hand, such as how a small change in work team availability affects the number of outages needed.
ElectraNet now plans 18 months ahead instead of 13, and can change its own business rules with little or no input from Daitum.
“Daitum has helped us to make a complex problem easier to understand. Our maintenance plans now take less time to develop, yet are even more robust.”Simon Cole, Senior Maintenance Planner, ElectraNet
Book a demo
Book a 30-minute call. Tell us how you schedule now, and we’ll show you what would change.