Case study · ElectraNet

Outage planning, five times faster.

ElectraNet owns and operates South Australia’s high-voltage transmission network. Daitum plans the thousands of work orders that need a network outage.

Sector Energy transmissionModel Self-servicePlan Rolling outage plan

5x

Faster planning

1 FTE

Freed up in the planning team

35%

More months planned

18 mo

Planning horizon, up from 13

The challenge

Once a month, ElectraNet builds a rolling outage plan for the thousands of work orders that need a network outage. The plan has to group outages efficiently so customers see as few interruptions as possible. That means:

  • Matching service provider resources with work demand
  • Planning work when the chance of getting the outage is high
  • Finishing work orders close to their set point and never outside their float dates
  • Managing concurrent outages of critical transformers and lines
  • Linking work orders that share a piece of equipment

Before Daitum, one high-level plan could take weeks, and urgent corrective work wasn’t always planned well.

The solution

ElectraNet’s planning rules and KPIs were captured in a Daitum model, with the KPI weightings fully adjustable as the network changes. Work team availability, network risk ratings and outage groupings are uploaded alongside the work orders.

Daitum then chooses the month for each work order and which other work should happen at the same time, respecting every constraint. Planners run what-if scenarios with different KPIs to compare plans.

The result

More efficient outage groupings mean fewer planned outages for the same volume of work, which reduces network risk. Plans are five times faster to build, so planners can test scenarios that were impossible by hand, such as how a small change in work team availability affects the number of outages needed.

ElectraNet now plans 18 months ahead instead of 13, and can change its own business rules with little or no input from Daitum.

“Daitum has helped us to make a complex problem easier to understand. Our maintenance plans now take less time to develop, yet are even more robust.”Simon Cole, Senior Maintenance Planner, ElectraNet

Book a demo

See how Daitum would handle your week.

Book a 30-minute call. Tell us how you schedule now, and we’ll show you what would change.